Godavari Project

A project for providing drinking water to habitations in Godavari and Pusur segments-covering Bhadrachalam, Pinapaka, Aswaraopet, Sathupally (part), Kothagudem, Yellandu, Wyra(part) and constituencies of Khammam district of Telangana State

 

Project Value: 1352 Cr

 

The scope of work includes construction of Sumps/GLBR/GLSR 47330 KL, OBHR/ELSRs/OHSRs 1620 KL, DI Pipeline 570.51 km, HDPE Pipeline 2044.45 km, BWSC Pipeline 44.38 km, PCCP Pipeline 74.41 km, MS Pipeline 60.774 km, Water treatment plant (RSF) 134 MLD, pump houses (24), watchmen quarter (13), and compound wall at 11 locations.

 

The duration of the project is 30 months and the total population covered under this scheme will be 12, 95,000 from 1890 villages. Operation and maintenance will be for 10 years including a defects liability period (DLP) of 5 years.